Environmental Engineering

Sandy Point Wastewater Treatment Facility

  • Environmental Assessment for “one-of-a-kind project” in NC which required special legislative action
  • Cavanaugh selected by Steve Levitas (former NCDENR Deputy Secretary) based on Cavanaugh’s success with NCDENR Express Permitting
  • Design and Permitting of 600,000 gpd Sequencing Batch Reactor (SBR) wastewater treatment facility
  • Non-discharge facility
  • 300,000 gpd dispersed to spray irrigation field
  • 300,000 gpd transferred to infiltration basin
  • Design completed in 6 months
  • Received technical approval of permit in 6 weeks